Overlay Welding of Roller Press Squeeze Rollers for Final Grinding Slag

Overview of Slag Grinding Technology

Slag grinding is a critical process in cement manufacturing, where ground granulated blast furnace slag (GGBFS) is ground to a fine powder for use as a supplementary cementitious material. Modern cement plants use roller presses combined with vertical mills or ball mills for slag grinding, achieving high efficiency and low energy consumption. The roller press squeeze rollers are subjected to extreme abrasion from hard slag particles, requiring robust overlay welding for wear protection.

Slag grinding presents unique challenges compared to cement or raw material grinding:

Technical Requirements for Slag Grinding Overlay

The overlay welding requirements for slag grinding roller press squeeze rollers are the most demanding among cement grinding applications:

Overlay Material Selection for Slag Grinding

The selection of overlay material for slag grinding is critical and must balance hardness against toughness:

Material Type Composition Hardness (HRC) Abrasion Resistance Impact Resistance Suitability for Slag
W-C type Fe-W-C 60–70 Excellent Low Good for severe abrasion
Fe-Cr-B type Fe-Cr-B 55–65 Excellent Low Good for high abrasion
Cr-Cr2C6 type Fe-Cr-C 55–62 Very good Moderate Acceptable for moderate abrasion
Ni-Cr-Mo type Ni-Cr-Mo 45–55 Good High Not recommended for severe abrasion

For slag grinding applications, the W-C type overlay material is generally preferred due to its excellent abrasion resistance and ability to withstand high compressive stress. However, the low toughness of W-C materials requires careful control of welding parameters to prevent cracking.

Welding Procedure for Slag Grinding Rollers

The overlay welding procedure for slag grinding roller press squeeze rollers involves the following steps:

Step 1: Surface Preparation

  1. Remove the existing worn overlay by grinding or milling, exposing sound base metal.
  2. Clean the surface using wire brushing and solvent cleaning to remove scale, rust, and contamination.
  3. Preheat the base metal to 250–350°C using portable heating elements or gas torches.
  4. Inspect the prepared surface using magnetic particle testing (MT) to detect cracks or defects.

Step 2: Binder Layer Deposition

Parameter Value
Welding process SAW (Submerged Arc Welding)
Welding wire Low-carbon nickel-based alloy, 2.5 mm diameter
Flux Low-hydrogen flux, pre-dried at 300°C for 2 hours
Current 450–600 A
Voltage 26–32 V
Travel speed 200–300 mm/min
Layer thickness 2–3 mm total (2 passes)

Step 3: Overlay Layer Deposition

Parameter Value
Welding process SAW (Submerged Arc Welding)
Welding wire W-C type, 2.5 mm diameter
Flux Specialized flux for W-C alloy, pre-dried at 300°C for 2 hours
Current 500–700 A
Voltage 28–34 V
Travel speed 200–350 mm/min
Layer thickness 3–5 mm per pass
Total overlay thickness 8–12 mm
Interpass temperature 150–250°C

Step 4: Post-Weld Heat Treatment

  1. Cool the welded roller slowly under an insulated blanket at a rate of less than 50°C per hour.
  2. After cooling to ambient temperature, apply stress-relief annealing at 600–650°C for 4–6 hours.
  3. Cool again under insulated blanket at a rate of less than 50°C per hour.

Defect Analysis and Countermeasures for Slag Grinding Overlay

The following defects are commonly encountered in slag grinding overlay welding and should be prevented:

Defect Cause Detection Method Countermeasure
Cracking High carbon content, excessive heat input, rapid cooling MT, UT Use low-carbon binder layer, maintain interpass temperature, slow cooling
Porosity Moisture in flux, inadequate shielding PT, MT Dry flux thoroughly, ensure proper gas shielding
Incomplete fusion Insufficient preheat, excessive travel speed UT, MT Increase preheat to 300°C, reduce travel speed by 20%
Excessive hardness Too many overlay layers, no stress relief Hardness test Limit overlay thickness to 10–12 mm, apply stress relief
Surface irregularity Inconsistent travel speed, poor technique Visual, CMM Use welding positioner with constant speed, train operators

Quality Control and Inspection Protocol

A rigorous quality control protocol is essential for slag grinding overlay welding:

  1. Pre-weld inspection: Visual examination and MT of the prepared surface to detect cracks or defects.
  2. In-process monitoring: Real-time tracking of welding parameters (current, voltage, travel speed) and visual inspection of each pass.
  3. Post-weld testing:

Engineering Practice Considerations

The implementation of overlay welding for slag grinding roller press squeeze rollers requires careful attention to several practical factors:

Study Reflection and Key Takeaways

The study of overlay welding for roller press squeeze rollers in final grinding slag applications reveals that the technology demands the highest level of process discipline and quality control among cement grinding applications. The W-C type overlay material offers the best abrasion resistance for slag grinding but requires careful control of welding parameters to prevent cracking. The binder layer is critical for preventing cracking at the base metal-overlay interface, and its composition must be carefully selected to match the thermal expansion coefficient of both the base metal and the overlay material. Engineers should establish a systematic approach to wear monitoring and overlay maintenance scheduling to maximize equipment availability and minimize unplanned downtime. The integration of overlay welding with predictive maintenance strategies can further optimize the performance and economics of slag grinding systems. Future developments may include the use of advanced powder metallurgy consumables with tailored microstructures for specific slag grinding applications, and the integration of robotic systems for fully automated roller repair.